ESS Cryomodule Meeting (CM14 status update)
Thursday 23 Nov 2023, 14:00
→
15:00
Europe/Stockholm
zoom
zoom
Cycle profile.pdf
meeting_W47_20231123.pdf
miyazaki_20231123.pdf
Hide
CM14 assembly in a progress in IJCLAB and expected to be departure on December, 18
th
. Estimated arrival date to FREIA is December, 21
st
.
Mykhailo will send shock loggers to IJCLAB shortly.
Frame and pumping stations (still unclear 1 or 2) will be send from ESS to FREIA before CM14 arrival.
Additional CTS test is requested, end-life time that can take 2-3 weeks additionally. More details about the CTS test need to be discussed later.
With the current estimation, CM14 will be tested at FREIA W51(2023) - W09 (2024), i.e up to the end of February.
During the test of CM14, Akira and new colleagues from ESS will participate the RF test.