ESS Cryomodule Testing Meeting
Thursday 17 Nov 2022, 14:00
→
15:00
Europe/Stockholm
meeting_W46_20221117.pdf
Hide
UU will cool down CM12 again for leak tests at cold in January 2023
Artur's group will bring the oil-sealed leak detector and will join the experiment
Preliminary procedure: staying at 4 K for some days to accumulate He, thermal cycle up to 20 K, and then go down to 2 K and do the same thing
IJCLab will not join
If the leak in CM12 is confirmed, CM10 must be checked as well
Rocio will bring shock loggers with her to use them for CM09's transport
CM13 is blocked by a broken chiller of klystron + coupler conditioning bench
The system is being fixed and assembly will be restarted in W49
The cavities (24&25) are ready and waiting in the clean room
CM14 requires the new set of double-wall tubes and they are still under farication
Nicolas reported that the stepper motor was again stuck at cold after fixing the "axial play issue"
Good news that the issue was not from the axial play
The newly designed adapter is mounted and was ok at warm and is being cooled down
ESS-IJCLab governing meeting will be held in two weeks time where all the issues will be discussed
There are minutes attached to this event.
Show them
.
The agenda of this meeting is empty