Because of venting accident in ESS, the spare CM14 is needed for installation in the tunnel as a replacement for CM02.
As CM14 arrived to FREIA with new type of motors, the motors re-assembly (to the old type) are required before cold test.
The plan at FREIA for CM14 need to be changed to the next: W10: disconnect CM14 and move outside of bunker. W11: ESS team will come to FREIA to change the motors with the tools. W12-16: FREIA will continue the usual tests with CM14.