ESS Cryomodule meeting
Thursday 21 Mar 2024, 14:00
→
15:00
Europe/Stockholm
zoom
zoom
meeting_W12_20240321.pdf
Hide
CM14
is under the test, vacuum pumping is ongoing and tomorrow the additional warm coupler conditioning is possible.
FREIA started He liquifier first time after long 2 months stop and plan to cooldown the CM14 during W13.
W13 is possible time for Artur's visit.
W14 is possible slot for ESS team and Akira visit to join MP conditioning and heat load measurement.
We are aiming to end CM14 and sent to ESS W16.