ESS Cryomodule Meeting (CM14 status update)

Europe/Stockholm
zoom

zoom

  1. CM14 assembly in a progress in IJCLAB and expected to be departure on December, 18th. Estimated arrival date to FREIA is December, 21st
  2. Mykhailo will send shock loggers to IJCLAB shortly.
  3. Frame and pumping stations (still unclear 1 or 2) will be send from ESS to FREIA before CM14 arrival. 
  4. Additional CTS test is requested, end-life time that can take 2-3 weeks additionally. More details about the CTS test need to be discussed later. 
  5. With the current estimation, CM14 will be tested at FREIA W51(2023) - W09 (2024), i.e up to the end of February.
  6. During the test of CM14, Akira and new colleagues from ESS will participate the RF test. 