4th Follow-up meeting Gersemi
6 Jul 2017, 09:45
→
7 Jul 2017, 18:00
Europe/Stockholm
Cryo Difussion
Cryo Difussion
49 Rue de Verdun, 27690 Lery France
Thursday, 6 July
Thu, 6 Jul
Fri, 7 Jul
Planning and Critical Path
Current planning schedule with milestones
Deviations from initial planning
Critical paths
Convener
:
Adrien Striebig
more information
2017-07-05_-_-Gersemi_Cryostat_Light_Planning0--expanded(2).pdf
2017-07-05_-_-Gersemi_Cryostat_Light_Planning0--expanded.pdf
2017-07-05_-_-Gersemi_Cryostat_Light_Planning0--from20170701.pdf
2017-07-05_-_-Gersemi_Cryostat_Light_Planning0--.pdf
slides
12:00
Lunch Break
Visit of the premises
Manufacturing and Design Review
Magnet Insert design
Simulator box design
Final review vertical cryostat, valvebox and transfer lines
Conveners
:
ACS
,
Adrien Striebig
slides
Friday, 7 July
Thu, 6 Jul
Fri, 7 Jul
Control System
Planning
Tests status
Control and command procurement
Sequences
Conveners
:
Adrien Journiat
,
Konrad Gajewski
document
16P691-03-3152-100_-_Liste_equipements_2017_04_11.xlsx
cablage_BAV-_AJO_2017_01_23.xlsx
cablage_cryostat-_AJO_2017_01_23.xlsx
cablage_Insert_liquide_AJO_2017_01_24.xlsx
cablage_Insert_magnetique_AJO_2017_01_24.xlsx
12:00
Lunch Break
Control system (ctd.)
Planning
Tests status
Control and command procurement
Sequences
Conveners
:
Adrien Journiat
,
Konrad Gajewski