CM14 status was shown:
- CM14 arrived to FREIA December, 29th 2023
- Reception test is done
- Warm coupler conditioning was performed.
FREIA status: Cryoplant is under maintenance, the delay can be 2-4 weeks from now.
CTSs end-of-life test was discussed, the plan is presented by Nicolas:
- Motor fail expect after 200k revolutions.
- Need to run 2 motors at the same time in linear zone of tuning curve.
- Do not exceed motor temperature higher than 200 K.
- Need to track frequency continuously.
- Disengage system need to be checked in advance.
The ESS team would like to join the cold test in FREIA. The schedule will be clarified closer to the date.